Hi guys, we´ve implemented the "Approve Purchase Requisition" app in Fiori, everything seems to be ok. I could see the PR for the approval in Fiori, just like in the ERP. The thing is that i found that in the delivery date that shows in Fiori is different that the one that is showing in the Back end.
e.g.
Delivery Date for PR in Fiori --> 16/11/2014
Delivery Date for PR in ERP -->17/11/2014..
Different PR.
Delivery Date for PR in Fiori --> 11/12/2014
Delivery Date for PR in ERP -->12/12/2014..
It´s exactly a day before than delivery date in the ERP in every case.
Do you know what could be happening?